Projects
Briefly about the projects we have completed.

Molsberg tennis court
The client’s wish was to replace his old clay court with a new, maintenance-free surface. The choice fell on the Rebound Ace ConiRace system.
On the original court, we covered the old clay surface, installed new gravel and sloped. Then came the elastic layer of ConiRace and on top of that 4 layers of Rebound Ace Synpave.
- Scope of the project: 1 court 16x36m
- System used: Rebound Ace ConiRace
- Duration of implementation: 2 weeks
- Made: Spring 2024


Sports complex Oáza Říčany
In 2004, we installed the Rebound Ace GS8 se grand slam surface at the Oáza Říčany complex emollient 8 mm rubber. After 16 years, it was time to apply a new final coat of Rebound Ace Topcoat to speed up the game.
Smaller construction works were carried out here, such as filling smaller holes, removing irregularities, greasy stains and grinding the entire surface. Finally, we installed the final layer
- Scope of the project: 3 tennis courts 16x36m
- System used: Rebound Ace GS8
- Duration of implementation: 5 days
- Made: Fall 202


Mini court in a family house in Bratislava
In the spring of 2024, a client approached us with an unusual request. It was supposed to be the construction of a small tennis court right inside the family house. This immediately caught our attention and we accepted the challenge.
We supplied the client with all the necessary information and documents with instructions that needed to be completed before the actual implementation. For this project, we chose the Rebound Ace Synpave system designed for a wood foundation, which we installed on OSB boards with elastic rubber. The result was worth it!
- Project scope: 40m2
- System used: OSB boards and Rebound Ace Synpave
- Duration of implementation: 2 days
- Made: Spring 2024

Are you interested in a specific project?
Contact us and we will be happy to answer all your questions.